# Nebius Is Late on Microsoft's Data Center. The Contract Lets Microsoft Take Its Deposit Back.

canonical: https://vietphanx.com/archive/nebius-microsoft-refund
type: post
status: published
publishedAt: 2026-11-16T15:00:33.538Z
updatedAt: 2026-11-16T15:00:33.538Z
author: Viet Phan
authorUrl: https://vietphanx.com/me
image: https://media.vietphanx.com/media/1d0cdbed7fba3b0c64af54443ea83d6f3fa22f7d78542f44c2145d484ff77660.png
imageAlt: Nebius's revenue bridge: $146 million in Q3 2025, plus $510 million of growth in cloud and other revenue, plus a $325 million one-off partnership payment, to $981 million in Q3 2026; analysts expected $908 million
imageLicense: All Rights Reserved

## Provenance

- Canonical URL: https://vietphanx.com/archive/nebius-microsoft-refund
- Canonical status: canonical
- Source type: original

## Reuse / Citation

- License: All Rights Reserved
- Attribution required: yes
- Quote policy: short_quotes_ok
- AI search indexing: allowed
- AI training: unspecified
- Preferred citation: Nebius Is Late on Microsoft's Data Center. The Contract Lets Microsoft Take Its Deposit Back.. by Viet Phan. published 2026-11-16T15:00:33.538Z. https://vietphanx.com/archive/nebius-microsoft-refund. License: All Rights Reserved

Nebius's revenue rose 571%, but a third of it was one payment, and the New Jersey data center it is building for Microsoft has slipped into 2027. Microsoft's contract lets it cancel late parts of that site and get its upfront money refunded.

Nebius reported its third quarter on November 12. The headline numbers looked great.

Revenue was up 571%, and it beat what analysts expected.

The cloud business ran at a 53% adjusted profit margin.

Next year's forecast, $12–13 billion, came in above the $11.98 billion analysts expected.

Then the stock fell 17% that day, and another 10% the next. In two weeks, Nebius lost a quarter of its value.

That's a strange reaction to 571% growth.

The reasons are in the letter to shareholders, a few pages past the headline numbers. The biggest one points to a contract Nebius filed in April, with Microsoft, for a single data center in New Jersey.

The Quarter

Revenue was $981 million, against $146 million a year earlier. Analysts had expected $908 million, according to LSEG.

About a third of it came from one payment.

Nebius booked $325 million from a new kind of deal, where a partner builds the data center and Nebius supplies its software and know-how.

The company calls it non-recurring and hard to predict. An analyst from Wolfe Research asked about it on the call.

Without it, revenue was about $656 million, well short of that $908 million.

The payment also dwarfs the profit. Nebius made an operating profit of $50 million in the quarter, and that one payment was more than six times as big.

Nebius's revenue bridge: $146 million in Q3 2025, plus $510 million of growth in cloud and other revenue, plus a $325 million one-off partnership payment, to $981 million in Q3 2026; analysts expected $908 million

The same payment may have done even more for Nebius's favourite growth number.

Nebius used to sell its growth on ARR, a run-rate: the last month's cloud revenue, times twelve. It more than doubled in one quarter, from $3.0 billion in June to $6.4 billion in September.

Partnership revenue counts toward it, and Nebius doesn't say which month the $325 million landed in.

If it was September, that one payment, times twelve, would be $3.9 billion of the $6.4 billion. The rest would sit below June.

In the same letter, Nebius wrote this:


"We no longer see ARR as the right measure of our business."



One of its reasons was that partnerships "can add choppiness to ARR."

Nebius's ARR: $3.0 billion in June, $6.4 billion in September, about $2.5 billion in September if the whole $325 million one-off landed that month, against a February 2027 goal of $7 billion and an original December 2026 target of $7–9 billion

The target it had set on that measure slipped, too. A year ago, Nebius promised $7–9 billion of ARR by December 2026.

Now it expects "to exceed $7 billion" in February. After that, it will stop giving ARR targets.

This year's revenue forecast slipped to the low end of its $3.0–3.4 billion range. On the call, the finance chief put it at $3.0–3.2 billion.

Where the Money Goes

To grow into that $12–13 billion, Nebius plans to spend $40–45 billion next year.

It spent $7.3 billion in the third quarter alone. Even with customers paying ahead, the quarter used about $7.6 billion more cash than the business brought in.

Nebius's answer is that customers will fund most of the build.

It expects their prepayments, plus loans backed by their contracts, to cover 75–85% of next year's spending. On the deals it signed last quarter, it says, the prepayments covered more than the full cost of the equipment.

That still leaves $6–11 billion to find elsewhere. That's more than Nebius expects to earn in revenue this year.

Nebius's 2027 capital spending plan of $40–45 billion: prepayments and contract-backed loans cover 75–85%, leaving $6–11 billion uncovered, more than its 2026 revenue of $3.0–3.2 billion

So the plan works as long as customers keep paying ahead, and Nebius keeps delivering on time.

The Late Site

Delivering is where the quarter went wrong, and most of it happened in one place.

In September 2025, Microsoft signed up to rent Nvidia chips from Nebius for five years, all at a new data center in Vineland, New Jersey.

A developer called DataOne built the site for Nebius and runs it. Nebius fills it with servers, in batches.

The first batch was delivered in November 2025 and the second in February. More followed over the summer, until the power ran short.

The plan had been to run the site on DataOne's temporary generators while permanent fuel cells from Bloom Energy ramped up. Toward the end of the third quarter, DataOne began switching some of those generators off.


"DataOne decided to wind down the temporary generation faster than it was expected."
Andrey Korolenko, Nebius's chief product and infrastructure officer, on the November 12 call



Nebius now expects to deliver more than half of Microsoft's capacity by the end of this year. The rest has been rescheduled for the second quarter of 2027.

Delays at New Jersey and other partner-run sites are why some of this year's revenue moved into next year.

Timeline of Nebius's New Jersey site for Microsoft: contract signed September 2025, batches delivered November 2025, February 2026 and over the summer, temporary generators wound down early in late Q3 2026, more than half delivered by year-end, the rest rescheduled to Q2 2027

The Deposit

In its original form, Microsoft committed up to $17.4 billion over five years, across nine batches.

About $7 billion of that is paid up front, invoiced batch by batch, and Nebius uses that money to help pay for the build.

A January addendum added two more batches, with no upfront payment.

Think of a kitchen renovation.

You pay the builder a big deposit so they can buy the materials. The contract says what happens if they're late: a discount for every day, and after a while, the right to cancel and get your deposit back.

Nebius is the builder, and Microsoft is paying the deposit.

What the Contract Lets Microsoft Do

Section 3.3 of the contract is the renovation clause, and it works in four steps.

Late batch: if Microsoft hasn't accepted a batch by the end of its testing window, Nebius owes it a credit for every day after that.

Too late: once the batch misses a further grace period, or Nebius's own updates make that likely and it can't offer equivalent capacity elsewhere, Microsoft chooses. It can agree a new delivery date, or cancel that batch.

If it cancels: Nebius refunds the upfront payment Microsoft paid for that batch, minus the daily credits already paid on it, and Microsoft owes nothing more for it.

If it agrees a new date and Nebius misses that too: the batch counts as cancelled, unless both sides agree otherwise in writing.

Nebius's letter says all affected customers "have been kept informed throughout, and their plans are being accommodated."

Section 3.3 sets out what accommodating a late batch can cost.

What's Blacked Out

The filed contract hides exactly the parts that would size the risk:


how long the testing window and grace period run

how big the daily credit is

how much upfront money sits on the batches that are late


Nor does the record show that any of these steps has started.

On the call, CEO Arkady Volozh said none of the delayed capacity had been cancelled, and the letter says Microsoft is part of the planning.

Batches Microsoft has already accepted stay paid for, whether it uses them or not.

The Bill

The deposits show up in one more place.

At the end of September, Nebius's customers owed it $4.04 billion. That's twice the $1.96 billion of revenue it booked in the first nine months of the year.

That's possible because its accounting lets it bill customers in advance, before it delivers.

One customer owed 75% of it, about $3 billion.

Nebius doesn't say which customer it is.

Its share of revenue has grown every quarter this year, from about $84 million to $216 million. That's how Microsoft's would grow as the New Jersey batches go live.

But it's a fit with the numbers, and the filing never names it.

Customer D brought in 22% of Nebius's Q3 revenue but owed 75% of its receivables at September 30, about $3.03 billion; Customer E brought in 33% and owed 10%; all others 45% and 15%

The Forecast

Forecast from November 1: CoreWeave, Nebius, Oracle, Broadcom and Nvidia, in equal weights, trail the Nasdaq 100 on price return through October 2027.

Opened at the October 30 closes. By November 13, the five stocks were down 9.2% and the Nasdaq 100 down 1.6%.

That's 7.7 points in the forecast's favour.

Nebius is down 24.8% since then, the most of the five.

Closes on the last trading day of October 2027. Wrong if the five stocks match or beat the index.

Nebius has rescheduled the remaining New Jersey batches for the second quarter of 2027.

## Share / Canonical Links
- Canonical: https://vietphanx.com/archive/nebius-microsoft-refund
- JSON: https://vietphanx.com/archive/nebius-microsoft-refund.json
- Markdown: https://vietphanx.com/archive/nebius-microsoft-refund.md
- Share package: https://vietphanx.com/archive/nebius-microsoft-refund/share.json
- OpenGraph image: https://media.vietphanx.com/media/1d0cdbed7fba3b0c64af54443ea83d6f3fa22f7d78542f44c2145d484ff77660.png

## Related Records
- CoreWeave's Two Prices for Money: 16% on Its Own Name, 7% on Its Customers' (artifact, same_type): https://vietphanx.com/archive/coreweave-borrows-on-contracts
- The CFO Behind Nvidia's Circular Financing Now Runs Nvidia (artifact, same_type): https://vietphanx.com/archive/nvidia-kress
- Three Governors Already Froze Data Centers. 78% Chance Another State Does by June. (artifact, same_type): https://vietphanx.com/archive/data-center-freeze-2027
- Google's Cloud Doubled. And That's the Problem. (artifact, same_type): https://vietphanx.com/archive/google-cloud-doubled-problem
- AI needs every office worker on Earth to pay $205 a month. The typical company pays $15.70. (artifact, same_type): https://vietphanx.com/archive/ai-205-a-month
- Google's Czech Rival Built Its AI on a Google Model. The Textbook Fine-Tune Broke It. (artifact, same_type): https://vietphanx.com/archive/seznam-ai-meetup